Total Years of Experience: 29 Years, 5 Months
July 2008
To Present
Project Superintendent / Construction Manager
at M.S. Al-Suwaidi Industrial Services Co. Ltd
Location :
Saudi Arabia
Project/s:
Saudi Aramco - Bulk Plants Additional Capacity Phase II - Southwest Bulk Plants
Saudi Aramco - Upgrade Waste Water Treatment Plants (NSTP /AWWTP, Dhahran)
Duties & Responsibilities :
* Responsible for the day to day operation of the site civil & structural construction
works; plan, organize, direct and monitor site construction activities.
* Prepare construction work plans, methodologies, and schedule of activities.
* Prepare manpower and equipment requirement plans, initiate material requisitions
and ensure its timely availability on site for effective utilization of the resources.
* Coordinate with various departments such as QA/QC, Engineering/Design
departments, third party vendors, suppliers, and subcontractors. Initiate Request for
Inspections, submit Technical Appraisal of Materials, Tie-in Procedures, Test
Packages, raise Technical Queries, and propose Field Design Change as necessary.
* Supervise site construction activities, provide technical support and direction to the
construction team; ensure works are carried out in accordance with the approved
drawings, specifications and standards and ensure compliance to quality
requirements.
* Communicate and coordinate the plan, progress and status of the project in regular
basis in status reports and coordination meetings with the Proponent.
* Ensure safety at all times, prepare Job Safety Analysis, encourage a safe working
environment, and regularly conduct safety toolbox meeting with the crews.
Saudi Aramco - Bulk Plants Additional Capacity Phase II - Southwest Bulk Plants
Saudi Aramco - Upgrade Waste Water Treatment Plants (NSTP /AWWTP, Dhahran)
Duties & Responsibilities :
* Responsible for the day to day operation of the site civil & structural construction
works; plan, organize, direct and monitor site construction activities.
* Prepare construction work plans, methodologies, and schedule of activities.
* Prepare manpower and equipment requirement plans, initiate material requisitions
and ensure its timely availability on site for effective utilization of the resources.
* Coordinate with various departments such as QA/QC, Engineering/Design
departments, third party vendors, suppliers, and subcontractors. Initiate Request for
Inspections, submit Technical Appraisal of Materials, Tie-in Procedures, Test
Packages, raise Technical Queries, and propose Field Design Change as necessary.
* Supervise site construction activities, provide technical support and direction to the
construction team; ensure works are carried out in accordance with the approved
drawings, specifications and standards and ensure compliance to quality
requirements.
* Communicate and coordinate the plan, progress and status of the project in regular
basis in status reports and coordination meetings with the Proponent.
* Ensure safety at all times, prepare Job Safety Analysis, encourage a safe working
environment, and regularly conduct safety toolbox meeting with the crews.
August 2005
To May 2008
Site Civil Engineer
at Nokia Siemens Network GmbH
Location :
Libya - Tripoli
Project/s:
Akakus Oil Operations - NC115 Telecom Upgrade
GPTC - Border to Border Projects Phase III & IV
Duties & Responsibilities :
* Responsible for the overall operation of the civil and structural works; plan, organize
and monitor site construction activities, and supervise crews and subcontractors as
required to complete the project on schedule and within budget.
* Prepare technical specifications, inspection checklists, inspection test plan,
construction procedures and process control sheets.
* Prepare scope of works, construction work plans and schedule of activities with
resource and cost loading.
* Prepare estimates of quantities of materials, labor and equipment and develop cost
overview and analysis.
* Supervise site construction activities; ensure works are carried out in accordance
with the approved drawings and specifications and in compliance with quality
requirements.
* Monitor construction progress, prepare progress reports, evaluate against the plan
and propose necessary actions to keep the progress on the right path.
* Initiate request for inspection from QC and Client and coordinate with third party
testing facility for the required tests to close out the inspection checklists.
* Evaluate subcontractors and suppliers. Prepare subcontract and supply agreement.
Akakus Oil Operations - NC115 Telecom Upgrade
GPTC - Border to Border Projects Phase III & IV
Duties & Responsibilities :
* Responsible for the overall operation of the civil and structural works; plan, organize
and monitor site construction activities, and supervise crews and subcontractors as
required to complete the project on schedule and within budget.
* Prepare technical specifications, inspection checklists, inspection test plan,
construction procedures and process control sheets.
* Prepare scope of works, construction work plans and schedule of activities with
resource and cost loading.
* Prepare estimates of quantities of materials, labor and equipment and develop cost
overview and analysis.
* Supervise site construction activities; ensure works are carried out in accordance
with the approved drawings and specifications and in compliance with quality
requirements.
* Monitor construction progress, prepare progress reports, evaluate against the plan
and propose necessary actions to keep the progress on the right path.
* Initiate request for inspection from QC and Client and coordinate with third party
testing facility for the required tests to close out the inspection checklists.
* Evaluate subcontractors and suppliers. Prepare subcontract and supply agreement.
October 2004
To July 2005
Planning Engineer
at Hyundai Heavy Industries Co. Ltd
Location :
Nigeria
Project/s:
Bonny Crude Oil Terminal Integrated Project
Duties & Responsibilities :
* Prepare and maintain project schedules using Primavera Project Planner version 3.0
(P3).
* Develop progress measurement system. Monitor and evaluate progress according
to the system and generate progress reports.
* Update work schedules regularly. Evaluate and analyze the progress against the
schedule, identify current and future concerns and proposed necessary steps to
avoid deviation from the baseline schedule.
* Prepare forecasts and presentations of project status for construction management
and coordination meetings.
Bonny Crude Oil Terminal Integrated Project
Duties & Responsibilities :
* Prepare and maintain project schedules using Primavera Project Planner version 3.0
(P3).
* Develop progress measurement system. Monitor and evaluate progress according
to the system and generate progress reports.
* Update work schedules regularly. Evaluate and analyze the progress against the
schedule, identify current and future concerns and proposed necessary steps to
avoid deviation from the baseline schedule.
* Prepare forecasts and presentations of project status for construction management
and coordination meetings.
March 2001
To July 2004
Site Civil Engineer
at Siemens AG ICN
Location :
Libya - Tripoli
Project/s:
GPTC - Border to Border Projects Phase I & II
GMRA - Telecommunication Backbone System
Duties & Responsibilities :
* Responsible for the overall operation of the civil and structural works; plan,
organize, direct and monitor site construction activities.
* Prepare survey reports, evaluate site conditions, and gather actual topographic and
geologic data to aid the design team.
* Prepare design calculations for structures such as foundations for equipment,
shelters, tanks, solar panels, fencing, protections at road crossings etc.
* Prepare technical specifications, inspection checklists, construction procedures and
process control sheets.
* Prepare scope of works, construction work plans and schedule of activities with
resource loading and cost overview.
* Supervise site construction activities; ensure works are carried out in accordance
with the approved drawings and specifications and complies with quality
requirements.
* Initiate request for inspection from QC department and client’s representative and
coordinate with third party testing services to conduct required test and close out
the inspection checklists.
* Monitor construction progress, prepare progress reports and evaluate against the
plan and propose necessary actions to keep the progress on the right track.
* Evaluate subcontractors and suppliers. Prepare subcontract and supply agreement.
GPTC - Border to Border Projects Phase I & II
GMRA - Telecommunication Backbone System
Duties & Responsibilities :
* Responsible for the overall operation of the civil and structural works; plan,
organize, direct and monitor site construction activities.
* Prepare survey reports, evaluate site conditions, and gather actual topographic and
geologic data to aid the design team.
* Prepare design calculations for structures such as foundations for equipment,
shelters, tanks, solar panels, fencing, protections at road crossings etc.
* Prepare technical specifications, inspection checklists, construction procedures and
process control sheets.
* Prepare scope of works, construction work plans and schedule of activities with
resource loading and cost overview.
* Supervise site construction activities; ensure works are carried out in accordance
with the approved drawings and specifications and complies with quality
requirements.
* Initiate request for inspection from QC department and client’s representative and
coordinate with third party testing services to conduct required test and close out
the inspection checklists.
* Monitor construction progress, prepare progress reports and evaluate against the
plan and propose necessary actions to keep the progress on the right track.
* Evaluate subcontractors and suppliers. Prepare subcontract and supply agreement.
March 1996
To January 2001
Planning Engineer
at Dong Ah Consortium
Location :
Libya - Tripoli
Project :
GMRA - The Great Man-Made River Project Phase II
Duties & Responsibilities :
* Prepare, update and maintain working level project schedules. Submit weekly and
monthly look-ahead schedules to the project management and to client’s
representative.
* Develop construction progress measurement system. Monitor and evaluate
progress according to the system and generate daily, weekly and monthly progress
reports.
* Prepare process control sheets for each structure and gather all inspection
checklists.
* Prepare Progress Verification Certificates for claiming the payments for the progress
achieved.
* Provide technical support and direction to the construction team, interpret
approved drawings, create detailed sketches and raised engineering field change
request as necessary.
* Prepare construction work plans and procedures for client’s approval.
* Review drawings and prepare technical specifications for client’s approval.
GMRA - The Great Man-Made River Project Phase II
Duties & Responsibilities :
* Prepare, update and maintain working level project schedules. Submit weekly and
monthly look-ahead schedules to the project management and to client’s
representative.
* Develop construction progress measurement system. Monitor and evaluate
progress according to the system and generate daily, weekly and monthly progress
reports.
* Prepare process control sheets for each structure and gather all inspection
checklists.
* Prepare Progress Verification Certificates for claiming the payments for the progress
achieved.
* Provide technical support and direction to the construction team, interpret
approved drawings, create detailed sketches and raised engineering field change
request as necessary.
* Prepare construction work plans and procedures for client’s approval.
* Review drawings and prepare technical specifications for client’s approval.
May 1994
To January 1996
Site Civil Engineer
at SGM Construction
Location :
Philippines
Project/s:
School, Residential & Commercial Buildings, Roads & Public Works
Duties & Responsibilities :
* Prepare documents for project biddings.
* Estimate of quantity of materials, labor and equipment and prepare Bill of
Materials, schedules, and S-curves.
* Plan, organize, control and monitor day to day site construction activities ensuring
manpower and equipment are utilized effectively.
* Supervised site construction activities; ensure works are carried out in accordance
with the approved drawings and specifications.
* Provide technical support and direction to the construction team, interpret
approved drawings, and create shop or detailed sketches.
* Coordinate with various agencies for the necessary permits.
* Coordinate with the client regarding the project progress status and request for
billing and payment process.
School, Residential & Commercial Buildings, Roads & Public Works
Duties & Responsibilities :
* Prepare documents for project biddings.
* Estimate of quantity of materials, labor and equipment and prepare Bill of
Materials, schedules, and S-curves.
* Plan, organize, control and monitor day to day site construction activities ensuring
manpower and equipment are utilized effectively.
* Supervised site construction activities; ensure works are carried out in accordance
with the approved drawings and specifications.
* Provide technical support and direction to the construction team, interpret
approved drawings, and create shop or detailed sketches.
* Coordinate with various agencies for the necessary permits.
* Coordinate with the client regarding the project progress status and request for
billing and payment process.