Luis Mago, Production Responsible

Luis Mago

Production Responsible

ConVerpro

Location
Venezuela
Education
Diploma,
Experience
29 years, 5 Months

Share My Profile

Block User


Work Experience

Total years of experience :29 years, 5 Months

Production Responsible at ConVerpro
  • Venezuela
  • November 2010 to June 2012

Refinery construction at Puerto La Cruz Venezuela as RP. (Production Responsible).
Project over 485 MM $ (Phase I and II)

Mayor Preservation Consultant at PDVSA GAS
  • Venezuela
  • November 2009 to November 2010

Responsible over all the preservation teams and works to the entire project (PGA) (Fields CSR, CSJ, CZMT, CSA, main stores and warehouse) (1800 MM $) in order to guarantee the functionality of equipments during construction according to specification API-686.

Construction Superintendent at PDVSA - Project Gas Anaco
  • Venezuela
  • February 2005 to June 2009

Construction of the complex “Centro Operative San Joaquin” Installation of nine turbines Mars 100 to increases production to 1400 MQFD, and 36000 BPD of Crude Oil, coordination of all the activities between the ten different contractors working in the complex of Gas & Oil; recollections lines (100 km.) and pipe lines interconnection, also the modification of the five station of recollection to handle the increase of production; Project over 1200 MM $

Project Engineer at CCIC – Subcontractor
  • Qatar - Doha
  • January 2004 to May 2004

Construction activities of Train 4 utility area, LNG Plant.
Head of Plant Shut Down, Train 3 Flare repairs, 146mts high, I.D 42” & 64”.
Specifications followed ASME/ANSI, API, AWS, ASTM, Job Spec. Project over 1500 MM $

Preservation Material Maintenance Management, and Section Mechanical Engineer Utility Area. at FLOUR DANIEL – INELECTRA
  • Venezuela
  • February 2002 to January 2004

Responsibility over all the preservations teams, for the up grading plant of synthetic oil, (Use of new technology in Gas, Liquid and solid Corrosion inhibitors, Desiccants etc) during construction. Rotary and Stationary equipment installation using laser Tech. Vibration analysis etc, Design of routines and procedures for Preventive Maintenance, and Standardisation of lubricants, Leader of subcontractor’s teams for the Pre-commissioning activities of utilities areas. Specifications followed ASME/ANSI, API, AWS, ASTM & AMERIVEN Job Spec. Project over 870 MM $

Construction Coordinator Manager. at PDVSA GAS– Dit Harris. Consultant
  • Venezuela
  • July 2001 to January 2002

Construction of pipelines from oilfields San Joaquin, Santa Ana, Guario, El Roble to compression plats of Santa Ana 1, 2 and 3 as well of the Compression plant of San Joaquin, pipelines of 16” and 26” diameter and hot interconnection between Station and Plants. Anaco.
Pre-commissioning and commissioning activities.
Specifications followed ASME/ANSI, API, AWS, ASTM & PDVSA GAS Job Spec Project over 100 MM $

Section Mechanical Engineer at Foster Wheeler Contractor (DSD-CGI Subcontractor)
  • Venezuela
  • August 2000 to July 2001

Construction and installation of isometrics, Modifications of spools as required by process
Field Engineer in charge of Hydro testing and Pneumatic testing
Pre commissioning activities on COKE plant
Specifications followed ASME/ANSI, API, AWS, ASTM & Sincor / Foster Wheeler Job Spec. Project over 800 MM $

Preservation Materials Management at Kellogg Brown & Root- Parson- Technip- Dit Harris Contractor
  • Venezuela
  • November 1998 to July 2000

Preservation, Preventive and Corrective Maintenance. Corrosion Management for all facilities, responsible of all equipment used in the heavy oil plant up grading units, ( Utility, Coke, Crude up grader, Gas plant, Hydrogen plant, Sulphur plant etc) Rotary and Stationary equipment installation Design of routines and procedures for Preventive Maintenance. Leader of subcontractors teams for the Pre-commissioning activities of utilities areas. Standardisation of lubricants. Specifications followed ASME/ANSI, API, AWS, ASTM & Petrozuata. Project over 1200 MM $

Office Manager and Field Engineer. at CONOCO – Systems MULTIPLEXOR Consultant
  • Venezuela
  • September 1997 to November 1998

Coordination of construction activities in the 200 km of pipelines ( 36” and 20” I.D) Cross country pipelines from ZUATA to JOSE Inspection of Subcontractors during Construction of pipelines. Hydro testing, pre-commissioning and commissioning of pipelines.
Specifications followed ASME/ANSI, API, AWS, ASTM & Petrozuata Job Spec. Project over 500 MM $

Corporation Maintenance Manager. at R.M PROJECT
  • Venezuela
  • March 1994 to August 1997

Lead Engineer of the Maintenance Departments for Preventive and Corrective Maintenance. Design of maintenance routines for the subcontractors during operations. Supervision of subcontractors
Coordination of all the requirements to keep full operation

Mechanical Construction Manager at CABLE BELT – ABB- EDIVIAGRO Contractor
  • Venezuela
  • August 1989 to March 1994

Construction of a cable belt system to transport bauxite from the mine to field storage (I.P.C.) 4, 2 Km long with a drop of 394 Mts. Regenerative system at 4000 Ton per hour. Coordination of the mechanical design & Project Construction, Responsible of Commissioning and turn - over to the client. Project over 120 MM $

Project Mechanical Engineer, Maintenance Manager at EDIVIAGRO, C.A.
  • Venezuela
  • June 1984 to August 1989

Responsible for the maintenance and repairs of all the heavy equipment to support the construction sites. Maintenance and rebuild of asphalt plant, rock crushers and concrete plants, Mechanical Engineer, Maintenance Department high way Barlovento - Miranda. Conintur Dam - Tachira, Maintenance Department high way Valera - Trujjillo, Acarigua - Guanare and Guatire - Kempis

Section Mechanical Engineer – Preventive Maintenance at EDIVIAGRO, VINCCLER, TONORO Contractors
  • Venezuela
  • February 1982 to June 1984

Responsible for preventive maintenance over 2000 different types of heavy equipment, used in the dam construction of Guri. Design, construction and installation of the lubrication module to attend
all the equipment Construction, Installation, Training and Operation of Lubrication Lab spectrograph analysis, Dynamometers for diesel engines, Hydraulic test banks, Diesel injection test banks and Drill Training and Operation with Rotamec, injection of concrete to the base of the dam.
Project over 600 MM $

Education

Diploma,
  • at Buckinghamshire University.
  • April 1981

Specialties & Skills

Construction Management
Project Management
Consultant Coordination
Project Coordination
Construction Superintendent

Languages

English
Expert