SENIOR PLANNING & COST ENGINEER at Huta Marine Works Ltd.
  • Saudi Arabia
  • August 2014 to January 2018

• Reconcile and coordinate project cost data with client status reports.
• Develop necessary progress measurement report and progress monitoring tools for the project like progress chart, S-curve, weekly and monthly report.
• Maintaining and completing Project Key Performance Indicators.
• Writing detailed and summarized project progress reports.
• Identifying, costing and processing any contract variations.
• Updating progress in primavera (P6).
• Provides planning and cost controlling support for all projects which includes variation reporting, monitoring of milestone progress, and preparation of project billing process.
• Gathers and analyzes information to prepare reports on the progress of projects.
• Monitor daily site manpower, equipment, materials cost and production.
• Analysis of daily site production and its daily cost consumptions.
• Analysis of the planned budget and its actual production as per norms.
• Communicate with the project in charge and insure that the scheduled plan activities are implemented.
• Monitor site planned budget and compare to its actual site progress and its site cost consumption.
• Prepares for the weekly and monthly projects report for monitoring project activities regularly and communicate any issues that could delay or impeded the project promptly to the lead project engineer.
• Insure client requirements as per contract and standard are meet.
• Preparing the monthly invoice and back-ups.
• Involved in a weekly meeting with the client.
• Prepares the estimated forecast cost and cash flow till the completion of the project.
• Prepares for any corrective actions if required.
• Prepares for monthly management report (PMR).
• Prepares the monthly cashflow report.
• Managing and ensuring active engagement of team members by delegation of tasks to the appropriate person both on a long term on a day-to-day basis.

Project Control Engineer at Qatar Engineering W.L.L.
  • Qatar - Doha
  • February 2010 to May 2013

• Responsible for the project monitoring based on planned schedule.
• Develop necessary progress measurement report and progress monitoring tools for the project like progress chart, S-curve, weekly and monthly report.
• Writing detailed and summarized project progress reports.
• Identifying, costing and processing any contract variations.
• Generate project progress charts and cost reports.
• Updating progress in primavera (P6).
• Provides planning and cost controlling support for all projects which includes variation reporting, monitoring of milestone progress, and preparation of project billing process.
• Gathers and analyzes information to prepare reports on the progress of projects.
• Communicate with the project in charge and insure that the scheduled plan activities are implemented.
• Monitor site planned budget and compare to its actual site progress and its site cost consumption.
• Prepares for the daily, weekly and monthly projects report, monitoring project activities regularly and communicate any issues that could delay or impeded the project promptly to the lead project engineer.
• Evaluates the actual position of the project, compares the actual with the planned.

Project Control Engineer at Mohammad Al Mojil Group
  • Saudi Arabia - Jubail
  • January 2008 to January 2010

• Prepares quantity take-off for piping, electrical, and mechanical items.
• Tracking and coordinating progress of the project in daily basis and ensuring the project is on track.
• Monitoring cost and follow-up procurement items to meet the requirements on time.
• Prepares daily, weekly and monthly report.
• Tracking and coordinating progress of the project an daily basis and ensuring the project is on track.
• Monitoring cost and follow-up procurement items to meet the requirements on time.
• Involved in budget preparation, cost control, forecasting and cost reporting.
• Support forecast of time and cost problems by offering trending information.
• Determine schedule, estimates and work scope to execute and complete deliverables within budget.
• Verify scope trends and estimate costs by using contract terms.

Planning Engineer at Ginebra San Miguel Philippines
  • Philippines
  • September 2006 to December 2007

• Evaluates manufacturing processes by designing and conducting research programs; applying knowledge of product design, fabrication, assembly, tooling, and materials; conferring with equipment vendors; soliciting observations from operators.
• Provides manufacturing decision-making information by calculating production, labor, and material costs; reviewing production schedules; estimating future requirements.
• Prepares product and process reports by collecting, analyzing, and summarizing information
• Maintains product and company reputation by complying with government regulations.
• Maintains product and process data base by writing computer programs; entering data.
• Contributes to team effort by accomplishing related results as needed.
• Preparing the daily, weekly and monthly report.
• Monitoring raw material and making report through SAP system.

Specialties & Skills

AutoCAD
Website Management
Microsoft Excel
Primavera P6
Primavera operation and Microsoft Excel

Languages

English
Expert

Training and Certifications

Qatar Petrolium QP ID (Training)
Training Institute:
Safety Training
Baish Corniche Aramco Project ID (Certificate)
Date Attended:
December 2016
Shuquaic Power Plant Completion Certificate (Certificate)
Date Attended:
February 2017