Work Experience

Total years of experience :22 years, 3 Months

- construction manager - civil engineer Project manager - infrastructural manger at bein dayl
  • Saudi Arabia
  • My current job since June 2002

Specialization: Project Manager
Employment Record:

• From (June 2015_ Till now) in Saudi Arabia (BIN DAYEL company) Project manager engineer

• From (March 2009_May2015) in Saudi Arabia (AL MOUSA REA.E INVESTMENT) Project manager

• From (Jan 2007_ Feb 2009) in Saudi Arabia Project manager engineer (KFB Group

• From (Dec 2004 _ Dec 2006) in Saudi Arabia Project manager engineer (AL SWILAM Company)

• From (Feb 2002 _ Dec 2004) in Saudi Arabia Project manager engineer (AL Sawey Company)

• From (Oct 1998 _ Dec 2002) in EGYPT Site engineer at (Alexandria Company Talaat Mostafa)

Project Manager Construction Manager at BIN DAYEL
  • Saudi Arabia - Riyadh
  • My current job since June 2016

Project: construction GACA buildings - Duration: 36 months - 559, 643, 624 SR
project: construction Collage of Tourism at King Saud University - 24 months - 120, 530, 400 SR
Duties & Responsibilities :
Supervising the design of the organizational structure of the project workers
Coordinating, planning, and managing internal and external meetings about the project. and Attending meetings with the Client, Contractor, Consultants of the resident engineers, and the team members on the project and administration of the head office
Developing and managing effective communication and liaison with all relevant internal and external stakeholders to ensure that requirements are identified, assessed, and appropriately integrated into the project.
Ensuring senior staff/client is kept informed of important and relevant service/design decisions and that the objectives of the client are achieved.
Leading Weekly Progress Meetings with the Client, Contractor, and other team members;
Review and perform the duties and evaluations of the project team Performs staff.
Providing all necessary on-site directions, guidance, and instructions to control the project
Establishes an appropriate working relationship with the contractors and the team members
Reviewing Contractor’s technical submission offers
Administer the signed agreements during the life cycle of the project
A reported requirement for headquarter to the project requirement reported the manpower & Equipment reports for the required efficiency
Prepare and review the daily/weekly/monthly progress and HSE reports being raised to the client
Review work schedule and participate in work plan input and Prepare Project Management Plan
Reported actual work status report for the actual complete percent for management.
Reviews the Submittal monthly invoice to the Clint and subcontractor’s monthly invoice
Manage and control the Quality Assurance plan to achieve the required quality,
Emphasize the necessity of safety and ensure the implementation of all HSE requirements.
Coordinate and supervise the work of all activities and operations.

civil engineer - project manger at AL MOUSA REA.E INVESTMENT
  • Saudi Arabia - Riyadh
  • March 2009 to April 2016

project: construction of 10 Residential Buildings Apartments 120 -24 months- 78, 880, 650 SR in Riyadh
project: construction of Residential & Commercial Buildings (114 Apartments) in Riyadh for 24 months- 130, 880, 450 SR
project: construction of (commercial &official) Building 6 shops & 24 offices in Riyadh 18 months- 62, 230, 550 SR
Duties & Responsibilities :
Review shop drawings of the project and records the notes and receive supply materials according to required quantities &specifications
Review contract drawings for constructability Reported the manpower and the Equipment reports for the required efficiency
management and control of contractors in conformance with contract documents, drawings, and specifications and reviewed, approve, and process all technical submittals.
Monitor the testing and commissioning process of all works and - Conduct the final inspection of the work
approve the contractors' as-built drawings and ensure all materials and equipment meet the required specifications
Approve the method and scope of work for all project items before implementation
Maintaining project documents by Company and Client requirements
Follow up and review the project procurement status;
arranged with suppliers Organize with steel &concert factory before supply prepare workshop sketches for steel bars and bending
Check and review Bills of quantities and make a statement of savings and decrease after the actual inventory of the quantities of approved shop drawings
Review and ensure timely submission of the Company’s invoices
Review supplier invoices according to required quantities and specifications
Monthly check imports & exports for materials in stores

Project manager at KFB Group
  • Saudi Arabia
  • March 2007 to February 2009

project: construction of 2 new buildings in Al MALAZ Prison -24 months- 80, 830, 450 SR
Coordinated supply chain and procurement
processes to meet budget needs.
Controlled costs allocated for plant, labor, and materials.
Managed and led a team of staff to continuously achieve and exceed KPI targets.
Implemented method statements and risk assessment reporting.

Project manager at AL SWILAM Company
  • Saudi Arabia
  • February 2002 to January 2007

project: construction of 2girl's schools -24 months- 12, 730, 450 SR
project: construction of an education building in a college of general authority-24 months- 18, 330, 450 SR
Carried out quality control checks, ensuring \[Type\] specifications were consistently met.
Ensured consistent adherence to site health and safety protocol for continued staff well-being and compliance
Closely monitored progress, implementing necessary changes and enabling the completion of program deadlines.

Project manager
  • Saudi Arabia
  • February 2002 to December 2004

Education

Bachelor's degree,
  • January 1998

Education: -Graduation from Zagazig university faculty of engineering

Bachelor's degree, هندسة مدنية
  • at جامعة الزقازيق -مصر
  • January 1998

Education: -Graduation from Zagazig university faculty of engineering

Bachelor's degree, Civil Engineering
  • at zgazig universty (Egypt)
  • January 1998

Specialization: Project Manager Employment Record: • From (June 2015_ Till now) in Saudi Arabia (BIN DAYEL company) Project manager engineer • From (March 2009_May2015) in Saudi Arabia (AL MOUSA REA.E INVESTMENT) Project manager • From (Jan 2007_ Feb 2009) in Saudi Arabia Project manager engineer (KFB Group • From (Dec 2004 _ Dec 2006) in Saudi Arabia Project manager engineer (AL SWILAM Company) • From (Feb 2002 _ Dec 2004) in Saudi Arabia Project manager engineer (AL Sawey Company) • From (Oct 1998 _ Dec 2002) in EGYPT Site engineer at (Alexandria Company Talaat Mostafa)

Specialties & Skills

Site Engineering
Management
civil engineer
AutoCAD
Construction Engineering
ACADEMIC
ARCHITECTURAL DESIGN
CONSULTING
CUSTOMER RELATIONS
FRAMING
INVENTORY MANAGEMENT
LAYOUT DESIGN
LIGHTING
LOTUS NOTES
on site
project execution

Languages

Arabic
Expert
English
Expert

Training and Certifications

primavera & pmp v5 (Training)
Training Institute:
مركز

Hobbies

  • Good coordinate skills between multi design disciplines
    - Good coordinate skills between multi design disciplines - Nice attitude to receipt and deal with clients. - Good in work at the large-scale project and multipartite staff. - Working at high pressure and good work with team work.