Nabil CHATAT, Project Manager

Nabil CHATAT

Project Manager

Confidential

Lieu
Émirats Arabes Unis - Abu Dhabi
Éducation
Baccalauréat, Field Engineer
Expérience
28 years, 10 Mois

Partager Mon CV

Empêcher usager


Expériences professionnelles

Total des années d'expérience :28 years, 10 Mois

Project Manager à Confidential
  • Koweït - Al Jahra
  • Je travaille ici depuis décembre 2016

Project Manager And Contract Administrator FIDIC Red Book 23 Million Usd
The Works comprise the Construction, Completion and Roads, Utilities, Irrigation Tank Pump Station, Substations and Infrastructure Works
Works including:
All Roads Fresh Water and Fire Fighting Network. - Irrigation Water Network. - Sanitary Water Network. - Storm Water Network- Electrical Infrastructure Works and Telecommunication Work.

Underground water treatment plant, Irrigation Tank and Pump Room
All associated Structural, Architectural, Mechanical and Electrical Works.
Electrical Substation

Project Manager (PMP Certified) /Sr Project Manager à Orion contracting company
  • Émirats Arabes Unis - Abu Dhabi
  • août 2015 à août 2016

Construction of factory for producing Chlorine and Caustic soda For Union Chlorine in the Higher Corporation for Specialized Economic Zone “ZonesCorp” ICAD III, employing the latest state-of-the-art membrane technology and Distributed Control System. the work consited
Piling, Roads, Infrastructure, sbstructure, Superstructure, Undergroud Network, Storm Drainage, Pumping Station, Admin Building, Steel Structure, Fit Out, Industrial Mechanical, Electrical, Piping,
The plant commercial operation and the installed capacity of the plant is 70 TPD.

Project Manager / Sr.Project Manager / Avp Projects (Building Projects) à Al Jaber
  • Émirats Arabes Unis - Abu Dhabi
  • février 2014 à juillet 2015

Al JABER Energy UAE ONSHORE OFFSHORE Project Manager 400 MILLION USD OIL ANN GAS,
Construction infrastructure and Early Civil Work for Zakum Oil field manmade islands this Project is basically Early Civil Works and Infrastructure Development of the newly dredged ZADCO Manmade Islands namely North, Central, West & South.
This Project will pave the way for preceding Island activities like rig movement construction of a harbor area for material loading/unloading, helipad, material storage, office, drilling (plant area, rig access & pad area) and Island facilities (future Projector accommodations & related services).

Piling, Roads, Infrastructure, substructure, Superstructure, Underground Network, Storm Drainage, Pumping Station, Admin Building, Steel Structure, Fit Out, Industrial Mechanical, Electrical, Piping,

Project Manager / Sr.Project Manager / Avp Projects (Building Projects) à Air Liquide
  • Émirats Arabes Unis - Ras al-Khaimah
  • février 2013 à mars 2014

Project Manager 100 MILLION USD
Construction of factory For producing AST (Advanced sieve technologies) and pressure Tower for refinery of 60 meter long by 10 meter Diameter for gas production of Oxygen, nitrogen, liquid Nitrogen Liquid Oxygen Argon, Helium By cryogenic process

Piling, Roads, Infrastructure, substructure, Superstructure, Underground Network, Storm Drainage, Pumping Station, Water treatment Plant Admin Building, Steel Structure, Fit Out, Industrial Mechanical, Electrical, Piping

Reviewed plans and specs during the schematic design of pre-construction.Coordinated utility service providers according to project schedules.Obtained building and specialty permits from local jurisdictional agencies.
Conducted weekly production and operations contractor meetings, which facilitated stronger communication and
Conducted weekly production and operations contractor meetings, which facilitated stronger communication and the ability to resolve critical issues.

Project Manager / Sr.Project Manager / Avp Projects (Building Projects) à Kharafi National
  • Émirats Arabes Unis - Abu Dhabi
  • février 2011 à mars 2013

Project Manager 200 MILLION USD
Saadiyat island Project Sewage Treatment Plant -main swage pumping station MBR Technology Membrane Bioreactor R.O Technology 78000 m3, /day client ADSSC Abu Dhabi Sewerage Services Company (consortium) Kharafi national & EMIT (Italian)
Piling, Roads, Infrastructure, substructure, Superstructure, Underground Network, Storm Drainage, Pumping Station, Water treatment Plant Admin Building, Steel Structure, Fit Out, Industrial Mechanical, Electrical, Piping

Site Manager à Suez Degrmont
  • Egypte - Le Caire
  • octobre 2008 à septembre 2011

Project Manager .80.Million.Euro
waste water treatment of Gabal El Asfar Sewage Treatment Plant (300 000m3)/day Client MINISTRY OF HOUSING AND NETWORK, (consortium) Degremont -Arab Contractors (Egypt)
Piling, Roads, Infrastructure, substructure, Superstructure, Underground Network, Storm Drainage, Pumping Station, Water treatment Plant Admin Building, Steel Structure, Fit Out, Industrial Mechanical, Electrical, Piping

Project Manager / Sr.Project Manager / Avp Projects (Building Projects) à Suez Degremont
  • Algérie - Constantine
  • novembre 2007 à septembre 2008

Project Manager 30 Million Euro
Construction Potable Water Treatment Plant Ain Tinn BENI HAROUN transfer. Filter nitrification, Ozone, Activated Carbon, Pulsator, Chlorine (61 000m3 / J) Client Group ADE (consortium) Degremont CGC (Chinese)
Piling, Roads, Infrastructure, substructure, Superstructure, Underground Network, Storm Drainage, Pumping Station, Water treatment Plant Admin Building, Steel Structure, Fit Out, Industrial Mechanical, Electrical, Piping

Project Manager / Sr.Project Manager / Avp Projects (Building Projects) à Suez Degremont
  • Algérie - Constantine
  • février 2005 à février 2007

Project Manager 80 MILLION EURO
Construction Potable Water Treatment Plant of OUED ATHMANIA BENI HAROUN transfer .Filter soils, ozone, activated carbon, Pulsator, Chlorine (262 000m3 / J) Client (ADE). Algérienne des Eaux Consortium Degremont Enka (Turkey)
Piling, Roads, Infrastructure, substructure, Superstructure, Underground Network, Storm Drainage, Pumping Station, Water treatment Plant Admin Building, Steel Structure, Fit Out, Industrial Mechanical, Electrical, Piping

Site Manager à Suez Degremont
  • Liban - Tripoli
  • septembre 2003 à octobre 2005

Project Manager 20 MILLION EURO
Construction of Water Treatment plant city of Tripoli pre-treatment- biogas - Digester - sludge incinerator (300 000m3/day) client (CDR) Council Of Development And Reconstruction (consortium) Degremont BUTEC (Lebanese)
Piling, Roads, Infrastructure, substructure, Superstructure, Underground Network, Storm Drainage, Pumping Station, Water treatment Plant Admin Building, Steel Structure, Fit Out, Industrial Mechanical, Electrical, Piping

Project Manager / Sr.Project Manager / Avp Projects (Building Projects) à Suez Degremont
  • Maurice
  • avril 2001 à mai 2003

Project Manager 80 MILLION Euro
consortium coordinator, construction of Wastewater Treatment
Plant Client: (WASA) Water & Sewage Authority. Digester, Aeration, Settling, tank UV (8870.00m3 per hour) consortium G5 group, GCC, Manser Saxon, IBL (Italian, South Africa, Mauritian)
Piling, Roads, Infrastructure, substructure, Superstructure, Underground Network, Storm Drainage, Pumping Station, Water treatment Plant Admin Building, Steel Structure, Fit Out, Industrial Mechanical, Electrical, Piping

Project Manager / Sr.Project Manager / Avp Projects (Building Projects) à Suez Degremont
  • Yémen - Sanaa
  • juin 2000 à juin 2001

SITE Manager 30 Million Euro
Construction of Sana 'a Wastewater Treatment Plant .Client: (NWSA) National Water & Sewage Authority 60 000m3 / d Degremont group VINCI (DUMEZ GTM) (French)
Piling, Roads, Infrastructure, substructure, Superstructure, Underground Network, Storm Drainage, Pumping Station, Water treatment Plant Admin Building, Steel Structure, Fit Out, Industrial Mechanical, Electrical, Piping

Project Manager / Sr.Project Manager / Avp Projects (Building Projects) à Dumez GTM VINCI
  • Yémen - Sanaa
  • février 1999 à février 2000

Civil Engineering Construction waste water treatment plants Sana’a 'VINCI Degremont (JWG DUMEZ) Client: (NWSA) 60 000m3 / d
Piling, Roads, Infrastructure, substructure, Superstructure, Underground Network, Storm Drainage, Pumping Station, Water treatment Plant Admin Building, Steel Structure, Fit Out, Industrial Mechanical, Electrical, Piping

Site Manager à Dumez GTM Vinci
  • Arabie Saoudite - Riyad
  • janvier 1999 à décembre 1999

Construction of a highway Road
Construction Coordinator, QS, Planning Engineer, Claim Coordinator 36 Million USD(7) connection MAIDANI AL MALAK ROYAL PALACE OF DARIAY Client: ARiyadh Development Authority (ADA)
Piling, Roads, Infrastructure, substructure, Superstructure, Underground Network, Storm Drainage, Pumping Station, Water treatment Plant Admin Building, Steel Structure, Fit Out, Industrial Mechanical, Electrical, Piping

Site Manager à VINCI DUMEZ GTM
  • Arabie Saoudite - Jeddah
  • mars 1998 à mars 1999

Site MANAGER, 13 Million USD
Electrical connection for the pump station Project storm water drainage rainwater 5x5 m3 / second Client: (Ministry of Municipal and Rural Affairs.)

Project Coordinator Operation and maintenance Manager à Dumez GTM VINCI
  • Arabie Saoudite - Jeddah
  • février 1994 à février 1998

Operations and Maintenance Manager 10 Million USD
Storm water drainage plant of the city of Jeddah, Client (Ministry of Municipal and Rural Affairs.)


1994-1996 VINCI (DUMEZ GTM) Jeddah Saudi Arabia
Project Engineer, 120Million USD
Reviewed plans and specs during the schematic design of pre-construction., construction of Coordinated utility service providers according to project schedules. Storm Water Drainage Project Jeddah, Client (Ministry of Municipal and Rural Affairs) Construction of 13 km of reinforced concrete box culvert 6.90 meters by 3.60 meters Construction of pumping station capacity of 25 m3 per second
Under ground Utilities, Roads Technical Coordinator, local administrative authorities (Ministry of Water Municipality Ministry of PTT Communications • Ministry of Electricity, Ministry of transport, ) etc..
Piling, Roads, Infrastructure, substructure, Superstructure, Underground Network, Storm Drainage, Pumping Station, Water treatment Plant Admin Building, Steel Structure, Fit Out, Industrial Mechanical, Electrical, Piping

Éducation

Baccalauréat, Field Engineer
  • à IOST
  • mars 1986

Specialties & Skills

Team Leadership
Team Building
Technical Project Leadership
Construction Knowledge
Contract Management
Project Management
Auto CAD , MS project , EXCEL WORD
Cost Control
Project Management

Langues

Arabe
Expert
Français
Expert
Anglais
Expert

Formation et Diplômes

Contract Administration , Claim Management (Formation)
Institut de formation:
Driver Consult
Date de la formation:
February 2007
Durée:
21 heures
Certified International project Manager (Certificat)
Date de la formation:
February 2014
Valide jusqu'à:
January 9999

Loisirs

  • Technical certified Diver , Golf , Archery